Power/Energy Division

In order to generate sustainable and predictable income stream, JAKS has diversified into power generation on the international front in 2011, through JAKS Hai Duong Power Company Limited ("JHDP"). JHDP has been granted the Investment Certificate by the Ministry of Planning and Investment of Vietnam on June 2011 to develop a 2 x 600 MW Coal Fired Thermal Power Plant Project in Phuc Thanh Commune, Kinh Mon District, Hai Duong Province, Vietnam ("Hai Duong BOT Thermal Power Plant"), under the form of Build-Operate-Transfer ("BOT") for 25 years.


On August 2011, JHDP has successfully executed main project agreements for the Hai Duong BOT Thermal Power Plant, which include the BOT Contract, Power Purchase Agreement, Coal Supply Agreement, Land Lease Agreement, Government Guarantee and Undertaking Agreement with the Government of Vietnam and other government related entities.


On July 2015, JAKS formed a joint-venture with China Power Engineering Consulting Group Co Ltd ("CPECC"), an integrated power engineering service provider that have been involved in engineering and construction of approximately 49,000 MW of power plant projects, to jointly build and run the USD1.87 billion Hai Duong BOT Thermal Power Plant. (For more information on CPECC, please visit: www.cpecc.ceec.net.cn/)


Further to this, JHDP had in August 2015, awarded Golden Keen Holdings Limited ("GKHL"), a wholly-owned subsidiary of JAKS, the engineering, procurement and construction contract ("EPC Contract") for a contract sum of USD454.5 million. Under the EPC Contract, GKHL is responsible for the engineering, procurement and construction of certain key infrastructure assets that will support the Hai Duong BOT Thermal Power Plant.


Construction of Hai Duong BOT Thermal Power Plant has commenced in the first half of 2016. Hai Duong BOT Thermal Power Plant achieved the commercial operation for its first unit on November 2020, while the commercial operation for the second unit was achieved in January 2021.


Main plant
30'Mar'2021
Main plant 0 meters layer
30'Mar'2021
Acid and alkali tank
30'Mar'2021
Ash and slag handling system
30'Mar'2021
Coal discharger
30'Mar'2021
Coal terminal
30'Mar'2021
Electric dust removal
30'Mar'2021
Heavy oil pipeline
30'Mar'2021
Inspection boiler slag cooler
30'Mar'2021
Inspection boiler slag cooler
30'Mar'2021
Integrated corridor
30'Mar'2021
Pipe equipment
30'Mar'2021
Slag and Ash System
30'Mar'2021
Power cooling tower
30'Mar'2021
Power dry coal
30'Mar'2021
Power oil jetty
30'Mar'2021
Steam turbine
30'Mar'2021
Unloading coal terminal
30'Mar'2021
Water preparation acid and alkali torage tank
30'Mar'2021
Overall plant
31'Jul'2019
Boiler Unit 1 area
31'Jul'2019
Boiler Unit 2 area
31'Jul'2019
Installation for tubine Unit 1
31'Jul'2019
Installation for tubine Unit 2
31'Jul'2019
Main building
31'Jul'2019
Administration building area
31'Jul'2019
Administration building area
31'Jul'2019
ESP unit 1
31'Jul'2019
ESP unit 2
31'Jul'2019
Coal-limestone jetty are
31'Jul'2019
Oil jetty and Seawage water dicth
31'Jul'2019
Oil pump house area
31'Jul'2019
Intake water pump house area
31'Jul'2019
Water treatment area
31'Jul'2019
Ash silo area
31'Jul'2019
Workshop and warehouse area
31'Jul'2019
Lime stone crush house area
31'Jul'2019
Cooling tower area Unit 1
31'Jul'2019
Cooling tower area Unit 2
31'Jul'2019
Cooling pump house
31'Jul'2019
Cooling switch gear
31'Jul'2019
Switch yard area
31'Jul'2019
Dry coal shed steel structure
31'Jul'2019
Coal handling system
31'Jul'2019
Coal handling system
31'Jul'2019
Stacker – Reclaimer installation
31'Jul'2019
Coal handling control house
31'Jul'2019
Ash pond contruction
31'Jul'2019
Fire station
31'Jul'2019
Hydrogen station
31'Jul'2019